Malaysia Electric Locomotive Project which Handled by Western Union has completed the 2nd transportation.
2015-08-25
The CSR Electric Locomotives Co., Ltd Malaysia Electric Locomotive Project (the 2nd) which Handled by Western Union has successfully loaded on truck in the midnight of Aug 22, 2015; and the truck is on the way. Actual tracking status as below:
On Aug 21, hoisting for the cargo started from 21:00.
On Aug 22, the truck left CSR factory at 00:00; arrived at Pingxiang of Jiangxi Province at 06:00; arrived at Junshan Lake of Jiangxi Province at 19:00.
On Aug 23, the truck arrived at Dexin of Jiangxi Province at 03:00 and stayed a while for rest.
On Aug 24, the truck departed again.
On Aug 25, the truck arrived at Sanqing Mountain service zone of Jiangxi Province.